Foundation Work Update
August 2025Office foundation poured and pool brickwork complete, ready for September delivery.
Our unique location provides the perfect backdrop for transformative corporate retreats, enchanting weddings, and sophisticated events. An extraordinary destination where luxury meets purpose. Nestled in pristine surroundings, our unique location offers an unparalleled backdrop for transformative corporate retreats, enchanting weddings, and sophisticated events.
Office foundation poured and pool brickwork complete, ready for September delivery.
We visited Sydney showrooms last week to view finishes for both houses and gather samples for our final selections.
After getting the concrete poured earlier this week, we now have a proper crossing.
After months of waiting, the bridge finally got its concrete pour — and it's officially connected to the road!
The bridge is coming together fast and we're almost ready to pour the concrete!
Form work has officially begun on the property, kicking off the move from planning to real construction.
Screw piers are being installed, and additional bridge work is needed.
Interior design progressed with light and dark palette, plus detailed wardrobe, ensuite, and kitchen discussions.
Consecutive long weekends, trades not showing up and rain have caused some decent set backs.
Road progress continues with drainage pipes installed and road base delivered.
After heavy rain paused work, clear weather Tuesday allowed the crew to resume bridge preparations.
Road drainage began this week, while screw pier installation brought us closer to foundation pouring.
The construction is progressing well, with the first layer of the road now in place with pipes arriving this week.
Rock removal completed and passing lane now visible, thanks to the arrival of the hammer drill.
We've hit a little snag while cutting out the road.
This week marked a highlight as the team finally broke ground on the long-awaited road construction.
The site is in its final preparation stages as we gear up for road works to begin.
Heritage wall modifications and powder room designs progressed this week.
Primary pad detailing is underway while we clear site access and finalise construction certificate documentation.
We've received the first version of our construction drawings for review.
Taking advantage of a break in the weather, the team successfully completed the site survey.
Despite wet weather challenges, the team has returned for 2025 and made progress.
The lads are smashing through the earthworks - 2 weeks in.
Breaking ground! After many months of planning, we’re finally getting started with the earthworks.
Approval received for the changes we submitted and we are ready to start building.
We received our Stage 1 Design Development plans.
Plan modifications are required, so we need to submit changes to council for approval.
We have received council approval to begin construction on our dream home.
We've finished preparing all the documentation for our Development Application.
We found this property online, visited from Sydney, and were instantly hooked.